Commonwealth Scientific and Industrial Research Organisation
Published long after it started
- What it measures
- The contract notice was published more than six months after the contract’s start date.
- When it applies
- Publication more than 180 days after the start date, for contracts worth $100,000 or more. AusTender does not publish the date a contract was signed, so we measure from the start date and allow a wide margin. Notices published in a batch are counted under “Published late in a batch” instead.
- Why it matters
- The Commonwealth Procurement Rules require agencies to report contracts on AusTender within 42 days of entering into them.
- Common explanations
- A start date set earlier than signing, to cover work under an earlier arrangement. A lease or agreement republished under a new notice when it was renewed or varied. Administrative delay in reporting.
Showing Commonwealth Scientific and Industrial Research Organisation only. Show all agencies.
Contracts
Contracts published in 2025-26 and 2026-27 to date, largest amount first. Contracts with suppliers who are individuals are counted in the totals but not listed (why).
| Contract | Agency | Published | Detail | Amount involved |
|---|---|---|---|---|
| Lease from DISR CN4214057 |
CSIRO | 2026-01-19 | published 202 days after start | $17m |
| Lease to CSIRO - Dutton Park (Boggo Road) CN4263222 |
CSIRO | 2026-07-23 | published 5799 days after start | $12m |
| Lease to CSIRO - Bribie Island, QLD CN4263230 |
CSIRO | 2026-07-23 | published 5413 days after start | $4.3m |
| Land Purchase CN4213227 |
CSIRO | 2026-01-14 | published 194 days after start | $3.9m |
| Lease to CSIRO - Coopers Plains, QLD CN4263226 |
CSIRO | 2026-07-23 | published 5935 days after start | $3.2m |
| ANSIS Phase 2.0 Post Project Support CN4194303 |
CSIRO | 2025-10-14 | published 713 days after start | $3.1m |
| Research and Development Subcontract or Collaboration CN4226981 |
CSIRO | 2026-03-20 | published 262 days after start | $1.8m |
| Lease to CSIRO - IOMRC Crawley, WA CN4263235 |
CSIRO | 2026-07-23 | published 3579 days after start | $1.5m |
| ICT Labour Hire CN4277562 |
CSIRO | 2026-09-18 | published 360 days after start | $1.2m |
| Lease to CSIRO - Clayton - New Horizons, VIC CN4263231 |
CSIRO | 2026-07-23 | published 4829 days after start | $1.2m |
| Contractor (individual person hired via a supplier) CN4170865 |
CSIRO | 2025-07-16 | published 208 days after start | $916k |
| Secondment - Chief Scientist, Australia Telescope National Facility CN4210722 |
CSIRO | 2025-12-22 | published 315 days after start | $902k |
| Peer Review Design Services CN4190476 |
CSIRO | 2025-09-24 | published 1114 days after start | $882k |
| Research and Development Subcontract or Collaboration CN4257954 |
CSIRO | 2026-07-06 | published 2196 days after start | $812k |
| Heritage Monitoring Services CN4269602 |
CSIRO | 2026-08-17 | published 439 days after start | $800k |
| Palo Alto Firewall Services CN4230656 |
CSIRO | 2026-04-07 | published 188 days after start | $786k |
| Research and Development Subcontract or Collaboration CN4170670 |
CSIRO | 2025-07-16 | published 196 days after start | $785k |
| Sparked - Voronoi FY26-27 CN4275051 |
CSIRO | 2026-09-08 | published 1036 days after start | $748k |
| Research and Development Subcontract or Collaboration CN4228866 |
CSIRO | 2026-03-30 | published 272 days after start | $745k |
| Licence from CSIRO - Kensington, WA CN4214056 |
CSIRO | 2026-01-19 | published 232 days after start | $736k |
| Research and Development Subcontract or Collaboration CN4170626 |
CSIRO | 2025-07-15 | published 195 days after start | $704k |
| Project Management, Change Management and Comms professional Services CN4232261 |
CSIRO | 2026-04-13 | published 273 days after start | $693k |
| Temporary Personnel Services CN4179678 |
CSIRO | 2025-09-08 | published 413 days after start | $670k |
| Software CN4166140 |
CSIRO | 2025-07-02 | published 275 days after start | $633k |
| Fire Services - Armidale, Myall Vale, Narribri - NSW CN4209065 |
CSIRO | 2025-12-17 | published 330 days after start | $600k |
| Umbrella agreement - Cooperative framework in relation to the operatio… CN4206422 |
CSIRO | 2025-12-05 | published 1983 days after start | $600k |
| Research and Development Subcontract or Collaboration CN4239048 |
CSIRO | 2026-05-11 | published 376 days after start | $600k |
| Delivery of Experienced Leader Program CN4283853 |
CSIRO | 2026-10-21 | published 305 days after start | $592k |
| Research and Development Subcontract or Collaboration CN4265770 |
CSIRO | 2026-07-31 | published 1491 days after start | $585k |
| Argo Floats CN4178849 |
CSIRO | 2025-08-11 | published 262 days after start | $585k |
| ICT Labour Hire CN4224156 |
CSIRO | 2026-03-19 | published 350 days after start | $580k |
| Monash University Secondment Agreement CN4186837 |
CSIRO | 2025-09-09 | published 343 days after start | $569k |
| High Voltage Maintenance Services at Narrabri Armidale and Parkes CN4261267 |
CSIRO | 2026-07-15 | published 951 days after start | $558k |
| FHIR Specialist CN4166128 |
CSIRO | 2025-07-02 | published 904 days after start | $517k |
| Ethics digitalisation project CN4218674 |
CSIRO | 2026-02-10 | published 224 days after start | $507k |
| ICT Labour Hire CN4257316 |
CSIRO | 2026-07-03 | published 182 days after start | $477k |
| Secondment CN4187423 |
CSIRO | 2025-09-11 | published 559 days after start | $457k |
| Lease to CSIRO - IOMRC Watermans Bay, WA CN4263233 |
CSIRO | 2026-07-23 | published 3944 days after start | $452k |
| Mechanical Services Parkes CN4262464 |
CSIRO | 2026-07-20 | published 1602 days after start | $445k |
| Marine heatwave forecasting collaboration CN4174279 |
CSIRO | 2025-07-29 | published 1859 days after start | $440k |
| Globus - Data Mover CN4193026 |
CSIRO | 2025-10-07 | published 880 days after start | $439k |
| Solutions Implementation Services CN4280466 |
CSIRO | 2026-10-02 | published 200 days after start | $430k |
| Labour Hire CN4182462 |
CSIRO | 2025-08-22 | published 329 days after start | $426k |
| Implementation Support CN4167905 |
CSIRO | 2025-07-08 | published 314 days after start | $423k |
| HV Switch Upgrade at Waterford Site CN4281619 |
CSIRO | 2026-10-09 | published 281 days after start | $423k |
| ICT Labour Hire CN4257635 |
CSIRO | 2026-07-03 | published 182 days after start | $411k |
| Pilot Aquaculture Research Facility East Arm Berrimah, NT CN4273693 |
CSIRO | 2026-09-02 | published 420 days after start | $411k |
| Operational and Maintenance (O&M) Support to Tracking and Data Relay S… CN4229095 |
CSIRO | 2026-03-30 | published 1794 days after start | $411k |
| GPST Research Roadmap Implementation Admin (AR-PST) CN4228847 |
CSIRO | 2026-03-30 | published 302 days after start | $410k |
| High Voltage Maintenance Services – Lindfield CN4171583 |
CSIRO | 2025-07-18 | published 998 days after start | $409k |
| Legal Services CN4167419 |
CSIRO | 2025-07-07 | published 1832 days after start | $402k |