Federal Spending Explorer

National Health and Medical Research Council

Published long after it started

What it measures
The contract notice was published more than six months after the contract’s start date.
When it applies
Publication more than 180 days after the start date, for contracts worth $100,000 or more. AusTender does not publish the date a contract was signed, so we measure from the start date and allow a wide margin. Notices published in a batch are counted under “Published late in a batch” instead.
Why it matters
The Commonwealth Procurement Rules require agencies to report contracts on AusTender within 42 days of entering into them.
Common explanations
A start date set earlier than signing, to cover work under an earlier arrangement. A lease or agreement republished under a new notice when it was renewed or varied. Administrative delay in reporting.

Showing National Health and Medical Research Council only. Show all agencies.

Contracts

Contracts published in 2025-26 and 2026-27 to date, largest amount first. Contracts with suppliers who are individuals are counted in the totals but not listed (why).

ContractAgencyPublishedDetailAmount involved
Azure Consumption 25/25FY
CN4272082
National Health and Medical Research Council 2026-08-26 published 421 days after start $426k
ICT Labour Hire
CN4276652
National Health and Medical Research Council 2026-09-15 published 414 days after start $192k