What it measures
The contract notice was published more than six months after the contract’s start date.
When it applies
Publication more than 180 days after the start date, for contracts worth $100,000 or more. AusTender does not publish the date a contract was signed, so we measure from the start date and allow a wide margin. Notices published in a batch are counted under “Published late in a batch” instead.
Why it matters
The Commonwealth Procurement Rules require agencies to report contracts on AusTender within 42 days of entering into them.
Common explanations
A start date set earlier than signing, to cover work under an earlier arrangement. A lease or agreement republished under a new notice when it was renewed or varied. Administrative delay in reporting.

Showing Safe Work Australia only. Show all agencies.

Contracts

Contracts published in 2025-26 and 2026-27 to date, largest amount first. Contracts with suppliers who are individuals are counted in the totals but not listed (why).

ContractAgencyPublishedDetailAmount involved
Lease Agreement
CN4266363
Safe Work Australia 2026-08-04 published 399 days after start $3.1m
2024-25 MOU
CN4266367
Safe Work Australia 2026-08-04 published 727 days after start $2.1m
2024/25 SDO Services
CN4266368
Safe Work Australia 2026-08-04 published 764 days after start $1.3m
GovCMS Software as a Service
CN4266375
Safe Work Australia 2026-08-04 published 2676 days after start $833k
Ongoing ad-hoc advice
CN4266374
Safe Work Australia 2026-08-04 published 811 days after start $245k