Federal Spending Explorer

National Archives of Australia

Published long after it started

What it measures
The contract notice was published more than six months after the contract’s start date.
When it applies
Publication more than 180 days after the start date, for contracts worth $100,000 or more. AusTender does not publish the date a contract was signed, so we measure from the start date and allow a wide margin. Notices published in a batch are counted under “Published late in a batch” instead.
Why it matters
The Commonwealth Procurement Rules require agencies to report contracts on AusTender within 42 days of entering into them.
Common explanations
A start date set earlier than signing, to cover work under an earlier arrangement. A lease or agreement republished under a new notice when it was renewed or varied. Administrative delay in reporting.

Showing National Archives of Australia only. Show all agencies.

Contracts

Contracts published in 2025-26 and 2026-27 to date, largest amount first. Contracts with suppliers who are individuals are counted in the totals but not listed (why).

ContractAgencyPublishedDetailAmount involved
Variation 17 to utilise available extension period.
CN4252380
National Archives of Australia 2026-06-22 published 915 days after start $3.5m
Provision of electricity supply
CN4236617
National Archives of Australia 2026-05-03 published 685 days after start $150k
Legal Services
CN4236676
National Archives of Australia 2026-05-04 published 672 days after start $140k
Legal Services
CN4252265
National Archives of Australia 2026-06-22 published 704 days after start $100k