Contract notice CN4031127 · Department of Infrastructure, Transport, Regional Development, Communications and the Arts
Remediation of Slaughter Bay Sea Wall
+$1.2m (+219.8%) since first published at $532k
- Supplier
- DAVID EVANS ABN 12249379892
- Procurement method
- limited tender
- Reason given
- Valued below the construction threshold.
- Term
- 2023-06-26 to 2025-02-28
- Published
- 2024-01-29
- Category (UNSPSC)
- 72100000
- Agency reference
- 0041014644
Worth a closer look
Published long after it started: published 217 days after start. The Commonwealth Procurement Rules require agencies to report contracts on AusTender within 42 days of entering into them.
Common explanations: A start date set earlier than signing, to cover work under an earlier arrangement. A lease or agreement republished under a new notice when it was renewed or varied. Administrative delay in reporting.
Value increased after award: +220% on first published value. Agencies must publish amendments that change a contract’s value. Large increases can mean the original scope or price was understated.
Common explanations: Additional work or an extended term agreed after award. Options in the original contract that were later taken up. A correction to a value entered wrongly.
Value by financial year
The total value spread evenly from start to end date. estimate: annualised
| Financial year | Estimated amount |
|---|---|
| 2022-23 | $14k |
| 2023-24 | $1.0m |
| 2024-25 | $674k |
Published versions
Every version of this notice we have loaded. Source: AusTender OCDS API.
| Date | Version | Value |
|---|---|---|
| 2024-01-29 | original notice | $532k |
| 2025-03-11 | amendment | $551k |
| 2025-03-11 | amendment | $589k |
| 2025-03-11 | amendment | $904k |
| 2025-03-11 | amendment | $1.6m |
| 2025-03-11 | amendment | $1.7m |